Skip to page contents

Skip to Navigation


Data Annex

The table below provides summary statistics on the amount of time needed for moving projects in the CSI Program from either: application to project completion, application to reservation, reservation to installation, incentive claim request to payment approval, and from payment approval to payment issued. The table can be further refined to display these statistics by Program Administrator, host customer sector, and incentive type. Information on factors impacting administrative processing time is available here

This report is current as of April 16, 2014.

For summary statistics on average interconnection application processing times, and data on NEM penetration, see below.

Filters

Download filtered data

Display

Admin Metric

Project Completion
Application to Reservation
Installation
ICF processing (without Inspection)
ICF processing (with Inspection)
Payment

Host Customer Sector

All Sectors
Residential
Non-Residential

Admin

All Admin
CCSE
PG&E
SCE

Incentive Type

All
EPBB
5 Year PBI

Please select Admin Metric Filter to display table.

144,897 applications were included for the generation of this table. Data source: CSI Working Data Set

1The "95% within [days]" field displays the number of days within which 95% of the projects are processed for the selected metric. The value will be displayed in grey italics for months in which 20 or fewer applications were processed for that selected metric. See here for more information on how the 95th percentile is calculated.

This report is current as of Oct. 1, 2013.

Quarterly Average Interconnection Time

The table below provides summary statistics, by quarter, on the average number of calendar days it takes each utility to approve the interconnection of residential and non-residential customer projects.

PG&E SCE SDG&E
Quarter Residential Non-Residential Residential Non-Residential Residential Non-Residential
Q4 2013 14.2 16.3 22.4 14.7 4.9 5.4
Q3 2013 25.6 26.3 22.5 20.4 4.4 9.2
Q2 2013 14.7 22.0 12.2 11.6 5.2 3.9
Q1 2013 16.9 26.5 11.1 16.4 5.6 5.8
Q4 2012 22.3 19.9 13.1 15.3 5.1 2.6
Q3 2012 24.8 23.2 11.6 12.7 6.9 5.5
Q2 2012 20.8 17.7 10.5 23.0 5.1 5.3
Q1 2012 16.1 17.7 14.0 15.1 3.9 8.4
Q4 2011 14.4 15.9 25.6 32.4 5.4 5.9
Q3 2011 13.9 19.4 22.9 22.4 4.9 8.4
Q2 2011 10.3 14.3 19.0 23.0 5.5 4.2
Q1 2011 15.5 18.6 10.7 20.4 3.4 8.5
Q4 2010 24.7 18.4 6.3 13.5 2.9 4.2
Q3 2010 16.0 13.7 5.9 16.1 3.1 3.6
Q2 2010 6.7 8.6 3.3 14.9 3.5 5.0
Q1 2010 7.2 12.0 8.4 15.6 3.1 3.3
Q4 2009 7.5 10.7 6.6 10.8 2.8 3.5
Q3 2009 5.0 6.1 4.0 7.6 2.8 2.9
Q2 2009 2.7 7.4 3.7 19.9 2.7 3.3
Q1 2009 4.9 6.6 4.1 18.7 3.2 4.9


Monthly Average Interconnection Time

The table below provides summary statistics, by month, on the average number of calendar days it takes each utility to approve the interconnection of residential and non-residential customer projects.

PG&E SCE SDG&E
Month Residential Non-Residential Residential Non-Residential Residential Non-Residential
12/13 8.1 14.3 18.9 10.1 4.8 7.0
11/13 12.2 17.6 22.9 15.4 5.6 4.8
10/13 22.8 18.0 26.6 20.8 4.3 4.6
9/13 30.7 30.4 27.5 27.3 4.4 6.8
8/13 23.3 23.9 21.7 17.8 4.4 11.9
7/13 20.6 22.2 16.3 18.4 4.5 7.9
6/13 14.6 25.1 13.1 16.4 5.2 3.3
5/13 12.0 19.0 12.4 8.6 4.6 2.2
4/13 16.9 23.6 11.6 13.4 5.6 5.4
3/13 16.8 41.1 9.3 13.2 3.9 3.9
2/13 16.7 18.6 8.8 22.7 6.0 5.2
1/13 17.2 21.7 14.5 15.2 6.1 7.9
12/12 17.2 14.1 14.9 18.6 5.0 2.0
11/12 21.0 20.4 12.9 13.5 5.0 6.0
10/12 29.2 25.8 11.7 14.5 5.5 2.0
9/12 26.3 27.4 10.5 13.8 9.4 9.0
8/12 24.0 23.0 12.3 11.4 5.5 5.7
7/12 24.4 17.4 11.7 13.5 5.8 2.0
6/12 20.1 13.8 11.8 22.2 4.4 1.0
5/12 22.9 21.8 9.8 23.4 7.6 8.8
4/12 19.1 16.7 9.8 23.5 3.5 6.3
3/12 17.2 19.5 9.6 14.6 3.1 12.6
2/12 14.8 16.9 15.3 15.2 3.7 4.5
1/12 16.4 16.7 17.6 15.2 4.7 8.2
12/11 13.9 15.0 27.7 34.2 6.6 5.2
11/11 16.0 19.9 23.9 36.2 5.0 2.0
10/11 13.2 14.5 24.9 28.6 4.7 9.4
09/11 13.8 24.2 23.7 19.5 5.5 11.9
08/11 14.2 17.6 25.8 25.3 4.5 3.4
07/11 13.8 14.2 26.5 23.1 4.9 9.0

Data source: Utility data request
download as xls

Net Energy Metering Program Participation

The Public Utilities Code (PUC) Section 2827 establishes net energy metering (NEM) for solar and small wind customer-generators. NEM information for each IOU's service territory can be found at the following links.

Pacific Gas & Electric Company (PG&E)
Southern California Edison (SCE)
San Diego Gas & Electric (SDG&E) (select "NEM Cap" tab to view data)